Notes:
Mark Projects
Project Review Board (progress in Notes)
Moovila Adoption Updates/Action Items
August – resource management still in the works – doing Autotask automations first.
Resource Management
Ethan Bootcamp/Training/Test – August 15th
Mark 15th-17th (Friday 15th off) (Back Monday)
Wanson 28th-29th
Mark Goals for this week (8/11/2025)
Next Step for Q3 – Project Survey and Sign Off automations & template in DocuSign.
Resource management in Moovila
Communication to clients on the Signs offs and Surveys.
Went thru the templates – going to workflow/automate off a task.
Wanting to complete by Thursday. Going to test on test projects.
Thursday Update: Test worked – Workflow Task Title – Project Complete Survey and Status = Complete when a Task is Edited. He has the mail merge on the communication template working. Gave some template feedback – he is adjusting it a little.
Project Notes:
Autobarn LTD – Mazda – PC Refresh/End Point management – Signed off.
Doland Engineering – Wes & Ethan onsite today (Thursday) doing that.
Exchange – Switch upgrade – 6 total – this was approved. Waiting for hardware to show up. Should be in pretty quick. Waiting on Zacks approval on Dates. Kick off Call went well. _ need to approve some additional hardware – install August 14th.
Loeber – UPS – Install on Sunday.
Loeber – Switch upgrades – Thursday on tonight.
Autobarn Mazda Sales iPads – Waiting on Sign off.
Autobarn Volvo – Circle Lot – Waiting on Sign off – Juno Still needed to sign off
Audi HP Service Expansion – Need another quote from David to re-run a network drop – to route cabling up around the door neatly. (Project on Hold until Zack sorts out construction vendors)
Exchange – Highland Park – Service expansion –Talked with Zack on this as well. Moved the target date to Sept 6-7.
Exchange PC Refresh – Hardware is ordered – Rick sent follow up email this morning to ingram.
Exchange Switch – Audi Done, Porche next Monday, Chevy following Wednesday.
Exchange Porche Service Signal – Just got approved. Walk thru next week.
Slew of Firewall Refreshes – Looks like August 22nd for some inventory to open up – communication today on that.
Reviewed Quotes. (This is a standing note – only listing challenges going forward for Quotes)
Action Items:
In-Line
Completed by: George Fassett