Date:
12/19/2025
Type:
Zoom / Video Conference;Work Progress
Subject:
Projects <> Mark
Notes:
Mark Projects
Project Review Board (progress in Notes)
Moovila Adoption Updates/Action Items
Discussions in person next week when in town.
Resource Management
Doug 2nd & Wanson 6th off week of the December 22nd, back on Friday the 2nd and Monday the 6th of January
Ethan is off week of the 29th of December
Mark Goals for this week (12/31/2025)
Getting projects closed out before certification next week.
Getting Security initiative off the ground
SaaS Alerts
Need the Unified piece implemented. Advanced SIM piece we don’t currently license for, Nic wants us to do it. Kasaya Doesn’t want to sell it yet until after the 1st of the year.
SIM Licenses were released we have 1500 of them now.
Sam Certification – last one – MD102
Doug Passed Certification – MD102
Communication to clients on the Signs offs and Surveys.
Report doesn’t have project name
Wanson – might be able to show project names via MSPBOTS vs. built in Autotask report.
MSPBots making report – looked today and it is still not done.
Project Name – ID not included
Standing Discussions
Pro Services team – receive feedback from CruHu from customers.
Surveys as well – and can we do anything with CruHu.
Tams are more 1 dimensional that it can map back to a single ticket, making CruHu a good option but Pro Services project team CruHu is the wrong tool to measure their successes and criticisms.
Looks like Chevy Exchange is going to be sold. Zack included Chris on an email with some IT director guy. Ouch!
Turning Point going to build an expansion this coming year 2026- YAY.
Project Notes:
Calumet – SaaS – project – new – Wednesday the 7th kickoff
Calumet – New PC 6 refresh + Win 11 upgrades – Wednesday the 7th kickoff
Community Honda – SaaS Alerts Implementation – all policies enabled – SIM licenses are available – roll out with Wanson – Jan 6th.
Loeber – Mercedes – David got the speaker ordered for the music issue
Loeber – CoPilot implement – Kick off call w/ Mike Loeber – turn on 2nd week of January – Jen approved the licensing – Ethan is going to follow up to get that rolled out in January.
Mazda Orland Park – m365 implementation – everything done, everything is cut-over – policy issues breaking CDK – so we shut off policies and we need to get them re-enabled and troubleshooted.
Galactic Advisors – Sorted a bunch – punted to Mid-Jan – technology for zero trust and documentation on our rollout
Exchange PC Refresh –Ethan doing these in afterhours. Still have 7 left to do.
Reviewed Quotes. (This is a standing note – only listing challenges going forward for Quotes)
Action Items:
In-Line
Completed by: George Fassett