Date:

8/11/2025

Type:

Zoom / Video Conference;Work Progress

Subject:

Projects <> Mark

Notes:

Mark Projects

Project Review Board (progress in Notes)

Moovila Adoption Updates/Action Items

August – resource management still in the works – doing Autotask automations first.

Resource Management         

Ethan Bootcamp/Training/Test – August 15th

Mark 15th-17th (Friday 15th off) (Back Monday)

Wanson 28th-29th

Mark Goals for this week (8/11/2025)

Next Step for Q3 – Project Survey and Sign Off automations & template in DocuSign.

Resource management in Moovila

Communication to clients on the Signs offs and Surveys. 

Went thru the templates – going to workflow/automate off a task.

Wanting to complete by Thursday. Going to test on test projects.

Project Notes:

Autobarn LTD – Mazda – PC Refresh/End Point management – Signed off.

Community Honda – Sign off sheet now. Project complete. Waiting on Sign off.

Dan Wolfe UPS – Sam did it yesterday – wrapping up today and making sure things are good. I liked that we asked for a second opinion and it worked. Tom was frustrated his electrician said it needed a dedicated circuit.

Autobarn Imports – Print Services Migration – Sign off done.

Mazda of Orland Park – This is done

Doland Engineering – Hardware is dropping now.

Exchange – Switch upgrade – 6 total – this was approved. Waiting for hardware to show up. Should be in pretty quick. Waiting on Zacks approval on Dates. Kick off Call went well. _ need to approve some additional hardware – install August 14th.

DWG – Print Services Migration – Sign off completed and Survey.

Loeber – UPS – Waiting on Hardware.

Loeber – Switch upgrades – Looking at Thursday – looking for network modules which were ordered but we don’t have the hardware yet.

Autobarn Mazda Sales iPads – Waiting on Sign off.

Autobarn Evanston – Cabling & WAP installation today – Completed (not eligible for sign off)

Autobarn Volvo – Circle Lot – Waiting on Sign off – Juno Still needed to sign off

Shartega Firewall Refreshed – Installed – is done.

Audi HP Service Expansion – Need another quote from David to re-run a network drop – to route cabling up around the door neatly. (Project on Hold until Zack sorts out construction vendors)

Exchange – Highland Park – Service expansion –Talked with Zack on this as well. Moved the target date to Sept 6-7.

Exchange PC Refresh – Ingram & HP going back and forth for pricing – hasn’t been released yet. No official ETA from ingram on them dropping this week.

Exchange Switch – Audi tonight, Porche next Monday, Chevy following Wednesday.

Exchange Porche Service Signal – Just got approved.

Loeber UPS refresh – Now for the 17th.

Slew of Firewall Refreshes – there are some supply chain issues with the 3800s – those that aren’t in a supply chain problem – they are all getting scheduled. These are still B/O

Reviewed Quotes. (This is a standing note – only listing challenges going forward for Quotes)

Action Items:

In-Line

Completed by: George Fassett