Date:

5/29/2025

Type:

Zoom / Video Conference;Work Progress

Subject:

Projects <> Mark

Notes:

Agenda – Mark Projects

1.      Project Review Board

2.      Moovila Adoption Updates/Action Items

a.      Currently looking at End Dates

b.      Currently looking at Critical Paths on active projects

3.      Projects that are closing next 7-10 days (this week or next)

a.      Autobarn Imports – Windows updates

4.      Resource Management         

a.      Wes is out the week of the 16th.

b.      Doug has 2 weeks back to back last week of June/July

Notes:

Lucid – No internet yet – trying to get some hotspots up until fiber is installed – should get core up on Monday

Community Honda – approved Pc refresh – equipment ordered

Shartega – UPS received – not scheduled yet for Sam but there is a team meeting next Friday might be a good time to do that.

Doland – can’t reproduce the problem on our tenant like we were before – but it will reproduce on their tenant.

Autobarn – Team did good with service center – final piece now is migrating VM – tried last night – took too long – scheduled for Sunday

Looking for hardware on some of the projects.

Action Items:

None

Completed by: George Fassett