Date:

12/8/2025

Type:

Zoom / Video Conference;Work Progress

Subject:

Projects <> Mark

Notes:

Mark Projects

Project Review Board (progress in Notes)

Moovila Adoption Updates/Action Items

Discussions in person next week when in town.

Resource Management

Doug Called in Sick today (the 8th) – some concern on the validity of this

Wanson off 8th

Wes 12/19

Sam 12/15-12/19

Doug & Wanson off week of the December 22nd, back on Friday the 2nd of January

Ethan is off week of the 29th of December

Mark Goals for this week (12/08/2025)

Getting Security initiative off the ground

SaaS Alerts

Need the Unified piece implemented. Advanced SIM piece we don’t currently license for, Nic wants us to do it. Kasaya Doesn’t want to sell it yet until after the 1st of the year.

Goal is to have 2 done today, last 3 tomorrow.

Music Quote out to Sent this morning.

Communication to clients on the Signs offs and Surveys. 

Report doesn’t have project name

Wanson – might be able to show project names via MSPBOTS vs. built in Autotask report.

Pro Services team – receive feedback from CruHu from customers.

Surveys as well – and can we do anything with CruHu.

Tams are more 1 dimensional that it can map back to a single ticket, making CruHu a good option but Pro Services project team CruHu is the wrong tool to measure their successes and criticisms.

 

Project Notes:

Calumet – SaaS – project – new – internal kick off this Wednesday

***Community Honda – UPS – Finished – Scheduled close out call.

Community Honda – SaaS Alerts Implementation – No updates since Thursday

***Doland Engineering –Completed – Close out yesterday – went well Sent Survey this morning..

***Hiller Ford PC Refresh – Sent over a Close out meeting request – New PC’s will be another project once they approve. Scheduled for Wednesday.

Loeber – Mercedes/Porche – some DDR memory needed – been ordered – still waiting on hardware. Meeting with Sam today at 3:30 to get updates on these.

Loeber – CoPilot implement – Meeting scheduled with Ethan tomorrow to review.

***Lucid – Close out call was today – Survey send needed. New ticket off of Microsoft Tenant.

Mazda Orland Park – m365 implementation – Scheduled for catch up call with Doug.

Galactic Advisors – Meeting moved to Friday

Audi HP Service Expansion – Still on hold. Emailed on Friday to see if there is an update.

Exchange – Highland Park – Service expansion – On Hold

Exchange PC Refresh – About 23 machines left to do upgrades. Going to schedule some afterhours with Ethan to speed this up.

Exchange Porche Service Signal – Installation is today.

Reviewed Quotes. (This is a standing note – only listing challenges going forward for Quotes)

 

Action Items:

InLine

Completed by: George Fassett